Why overhead should not be figured as a percentage

Don’t get trapped

There are quite a few traps that people fall into when it comes to overhead and profit.  Perhaps it comes from a desire to simplify operations or a lack of follow through but one thing is certain: percentage based overhead calculations aren’t accurate most of the time.  It’s possible that a given percentage on a given project will end up covering the overhead costs for that project’s duration.  It’s just unlikely.

Overhead is not optional, imaginary, or driven by profit

Lets start with the nuts and bolts of overhead.  These are the costs of doing business.  Everything from office rent to printer paper get’s paid out of overhead.  Depending on how a company is structured, overhead may also pay the wages of staff members.  With rare exceptions, overhead costs are predictable and occur at regular intervals.

Why overhead should not be figured as a percentage

Like ammunition for example…

 

The key element I’d like to call attention to is that overhead must be paid as a function of time.  Rent will come due every month – it has nothing to do with how well the jobs are going.  As a bare-bones issue, overhead is a non-negotiable sum you must be earning at all times or you’re losing money.  Even non-profit companies MUST make overhead or they’ll go under.

Getting a handle on it

Figuring out overhead isn’t complicated, nor does it need to be.  I recommend taking the entire years worth of overhead costs (or projections) because some items are only payable annually.  For example a subscription to a trade publication, or the renewal fee for a license.  For companies with several years of records, I would encourage you to calculate the years separately to see year to year differences.  We’re looking to establish a baseline, not split hairs.

So annual costs (or projections) in hand it’s time to add for inflation and growth.  For the sake of simplicity let’s say that in an improving and expanding market, a 5% add is in order.  For a depressed market, it could be lower.  Unless you’ve got great reason to do so, don’t go negative.  Take this annual figure and divide by twelve for monthly overhead. Divide the total overhead by 52 for weekly.  Take your weekly and divide by five for working days.

Notice how I didn’t take the annual and divide by 365 to get days?  Working weekends isn’t typical for most businesses.  There are 260 working days (no holidays) in a year.  One way to handle the holidays is to assume 50 working weeks per year which give 252 working days per year.  The goal is to shift the overhead costs onto the working days.

Each job pays its own way

Now that we’ve got the daily overhead rate we need to answer some job specific questions.  First off, how many jobs will be going at the same time?  Each job needs to carry its fair share of the load.  Looking at company history to see what the average concurrent job count is will prove helpful here.  If there’s reason to believe you’ll have four projects going at all times, the overhead rate applied to each job should be a quarter of the total.  I call this office commitment. Be warned that each job is different.  If you’re looking at a very large job, it could consume all the companies resources for its duration.  Similarly, a “hurry up” job that requires you to drop everything would affect its bearing on your overhead.  You will quickly see that faster is cheaper.  A notoriously disorganized client, architect, or owner should indicate that a higher portion of your overhead costs will be attributed here.

Why overhead should not be figured as a percentage

Pictured above: A typical Owner, Architect, Contractor meeting.

Delayed gratification (and payment)

So are we done?  In a word, no.  The sad fact of the matter is that work is nearly never paid for as quickly as it’s done.  A standard practice in the construction industry is to withhold payment equaling 10% of contract value until the project is complete. A heavy equipment contractor would obviously complete their work well before a building is completed.  That contractor may not see full payment for several months!  Any financing costs arising out of their need to cover bills while awaiting final payment must be paid out of overhead which can be factored by the actual delay in getting paid.  Running a quick scenario, imagine it takes two weeks for that heavy equipment contractor to do a job and there’s about $1,000 a week in overhead for the operation.  If it takes sixteen weeks to get the last 10%  then $200 worth of the overhead is accruing interest for four months.  Let’s say it’s a credit card interest level of 15% which makes the additional cost $30 for the first month, $34.50 for the second month, $39.75 for the third month, and $45.64 for the last month.  Because it’s compounding, that delay ended up costing $149.89 to the contractor even if they got on to other projects while awaiting payment.

Taking stock of all these factors, you will arrive at a total overhead cost.  The overhead is not driven by how many people are working on site because those folks are job-billable.  The overhead is not driven by project cost because again, all of that is job billable.  Project duration, inflation, payout delay and office commitment are the only factors driving overhead.

Unintended consequences

Getting back to the headline of this article, I’d like to illustrate why percentile overhead calculations are so ruinous.  First off they work on the assumption that all jobs will consume overhead proportional to project cost.  This has the effect of charging too much overhead for jobs you’re really efficient at, and charging too little overhead for jobs you’re not as efficient at.  By extension this causes bids to run higher on jobs that more perfectly align with the companies abilities.  Conversely this causes bids to run lower on jobs that don’t align as well.

Let’s say we’re a company that furnishes and installs millwork.  There are two jobs to install millwork in commercial spaces.  One job specifies more expensive laminate material than the other but every other factor is the same.  Does it make sense therefore to bid a higher overhead amount for the nicer laminate?  Jobs are often won and lost by such amounts.  A set overhead percentage will only fit one dollar value perfectly.  Everything else is a bet against the future that you’ll pay for in lost overhead, or lost jobs.

For more articles like this click here

© Anton Takken 2014 all rights reserved

About Anton Takken

I chose to focus on estimating for a few reasons. Chief among them was that it's a position that's hard to fill in most companies. Job security and advancement is easier as a result. Unique to this job is a higher vantage point over the company and its place in the market. Bids are generally over in a few weeks which keeps things from getting boring. The reasons few of my colleagues pursue estimating comes down to a few misconceptions. The first is that it's the builders version of accounting - perceived as a lonely and quiet life among the charts and plans. The second is that it's not engaged in the construction process. Lots of the appeal of the construction industry is the sense that individual effort brought a plan into reality. The teamwork and camaraderie present among tradesman seems conspicuously absent at the estimators desk. Finally, I think the last reason is that it's daunting to be responsible for setting the price of something that's never been done. The good news for folks in estimating is that it's much more social than advertised. An estimator's phone is constantly ringing. Taking the opportunity to build relationships with the bidders creates a positive atmosphere and encourages everyone to do their best. It can be too much of a good thing which is why it's common to arrive at their voicemail when you're calling with a question. A strong rapport with the bidders can be invaluable. Subcontractors have much more exposure to what's going on in the market and they're often eager to share their knowledge. Learning from these experts is a priceless opportunity that's often overlooked. More on this in a bit. I decided to start this blog because I noticed that estimating has applications in many arenas. Over the last few years I've helped estimate in fields ranging from software development to blacksmithing! The more I thought about it, the more I realized that it's not about knowing what everything costs, it's about knowing how to figure that out. I believe the very first step to knowledge is to seek it, the second is to retain it, and the third is to pass it on. I hope to share some insights into how estimating is done and hopefully have some fun doing it. My experience is mostly commercial construction, but I'll try to make everything as generally applicable as I can. There are many aspects of business that all markets share yet it's remarkable that one of the most consistent is the failure to recognize that estimating is the very first step to a successful project. So if you're frustrated that work isn't profitable, or exasperated that there's never enough time to get the job done, this blog will be worth your time. Feel free to email me at: estimatorsplaybook@gmail.com View all posts by Anton Takken

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: